Câu 100: PRINCE2 Practitioner Edition 6

During previous projects, stakeholders became confused when using a number of separate project registers. Therefore, when preparing the risk management approach, the project manager created a risk register template and added it to an integrated project register. This register is a spreadsheet that includes project ass…

Nội dung câu hỏi

During previous projects, stakeholders became confused when using a number of separate project registers. Therefore, when preparing the risk management approach, the project manager created a risk register template and added it to an integrated project register. This register is a spreadsheet that includes project assumptions, issues, dependencies, and now risks, on separate pages. Is this appropriate for a risk register, and why?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Yes, because the project registers should be tailored to meet the needs of the organization. — đáp án hiện tại
  2. B. Yes, because risks are often identified as a result of issues being raised.
  3. C. No, because an integrated project register should include the quality register as well.
  4. D. No, because assumptions and dependencies are sources of risk.