The executive has asked the project manager to plan for the 'e-learning course' to be used as soon as it is accredited. The aim is to start selling the 'e-learning course' while the remainder of the outputs relating to classroom-based delivery are finished. The sales of the 'e-learning course' will be entered into the…
Nội dung câu hỏi
The executive has asked the project manager to plan for the 'e-learning course' to be used as soon as it is accredited. The aim is to start selling the 'e-learning course' while the remainder of the outputs relating to classroom-based delivery are finished. The sales of the 'e-learning course' will be entered into the business case. Why is the executive's decision to deliver the benefits early appropriate for managing the business case?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Because organizations with mature project management often include the early justification for the project in the business case.
- B. Because the outputs being delivered incrementally will be beneficial and will allow the business case to be justified. — đáp án hiện tại
- C. Because one of the PRINCE2 principles is that a project should focus on products to deliver the outputs early.
- D. Because the business case should be updated after every increment of the 'e-learning course'.