Câu 35: PRINCE2 Practitioner Edition 6

The project is now in stage 2. The Project Manager has heard about the possibility of a competitor also producing a calendar to be delivered earlier than the target date for this project. There is a threat that the early release of a competitor's calendar may weaken the impact of the MNO Manufacturing Company calendar…

Nội dung câu hỏi

The project is now in stage 2. The Project Manager has heard about the possibility of a competitor also producing a calendar to be delivered earlier than the target date for this project. There is a threat that the early release of a competitor's calendar may weaken the impact of the MNO Manufacturing Company calendar, thereby reducing the anticipated benefits of the Calendar project. Which 2 statements should be recorded under either the Records or Reporting headings?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Project Support will maintain the Risk Register.
  2. B. The evaluated net effect of all risks will be updated at the end of each stage and included in the End Stage Report. — đáp án hiện tại
  3. C. The Change Authority will report monthly to the Project Manager on the status of the change budget. — đáp án hiện tại
  4. D. Risks that are likely to occur within the next two weeks should be recorded as imminent.
  5. E. A summary of risks will be maintained and included with the monthly Highlight Reports to the Project Board.