CertyRush
Đang tải...
C CertyRush
Câu hỏi free preview

Câu 61: PRINCE2 Re-Registration

Which of the following statements about the Closing a Project process are true?1. The Closing a Project process provides a fixed point for the receipt of completed Work2. The Closing a Project process provides a fixed point to review if the objectives set out in the original Project Initiation Documentation have been…

Nội dung câu hỏi

Which of the following statements about the Closing a Project process are true?1. The Closing a Project process provides a fixed point for the receipt of completed Work2. The Closing a Project process provides a fixed point to review if the objectives set out in the original Project Initiation Documentation have been achieved. Packages for the work performed in the final stage.

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Only 1 is true
  2. B. Only 2 is true — đáp án hiện tại
  3. C. Both 1 and 2 are true
  4. D. Neither 1 or 2 are true

Cộng đồng

0 bình luận công khai. Tên thành viên được ẩn một phần.

Chưa có bình luận. Mở giao diện tương tác để bắt đầu thảo luận.

Câu hỏi liền kề