Câu 61: PRINCE2 Re-Registration
Which of the following statements about the Closing a Project process are true?1. The Closing a Project process provides a fixed point for the receipt of completed Work2. The Closing a Project process provides a fixed point to review if the objectives set out in the original Project Initiation Documentation have been…
Nội dung câu hỏi
Which of the following statements about the Closing a Project process are true?1. The Closing a Project process provides a fixed point for the receipt of completed Work2. The Closing a Project process provides a fixed point to review if the objectives set out in the original Project Initiation Documentation have been achieved. Packages for the work performed in the final stage.
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Only 1 is true
- B. Only 2 is true — đáp án hiện tại
- C. Both 1 and 2 are true
- D. Neither 1 or 2 are true