Câu 8: Salesforce Certified Business Analyst

The Salesforce development team is strictly following scrum to govern its releases. An executive trying to plan a vacation wants to know when work on the feature will begin so they can be available for additional implementation questions. After consulting with the product owner, the business analyst (BA) learns the te…

Nội dung câu hỏi

The Salesforce development team is strictly following scrum to govern its releases. An executive trying to plan a vacation wants to know when work on the feature will begin so they can be available for additional implementation questions. After consulting with the product owner, the business analyst (BA) learns the team has decided to adopt Kanban instead for all future releases. What should the BA tell the executive?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Work will begin after executive approval is given.
  2. B. Work will begin when capacity becomes available. — đáp án hiện tại
  3. C. Work will begin in the next sprint.