The business analyst (BA) at Universal Containers (UC) wants to understand why UC failed to meet a deployment date for its product go live while following the Agile process. According to the BA's research, the developers lacked a sense of the work in progress and the intended goal of that work, and the QA team was una…

Nội dung câu hỏi

The business analyst (BA) at Universal Containers (UC) wants to understand why UC failed to meet a deployment date for its product go live while following the Agile process. According to the BA's research, the developers lacked a sense of the work in progress and the intended goal of that work, and the QA team was unable to dearly test the functionality based on a given persona. Which step should the BA take next?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Create a SWOT (strength, Weakness, Opportunity. Threat) analysis to understand why development and testing took more time.
  2. B. Move the deployment date out so the teams have more time to work.
  3. C. Review the user stories to ensure they are small, testable, and valuable. — đáp án hiện tại