Câu 10: C-ACTIVATE13: SAP Certified Associate - SAP Activate Project Manager

Which estimation technique can be used in Agile Delivery Approach to size the User Stories during Sprint Planning?

Nội dung câu hỏi

Which estimation technique can be used in Agile Delivery Approach to size the User Stories during Sprint Planning?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Product Owner’s relative estimate of the effort that will be needed to implement the User Story
  2. B. Detailed bottom-up effort estimate that breaks each User Story up into hours or shorter tasks
  3. C. Relative estimate in Ideal Person Days that reflects the best estimate provided by the project team — đáp án hiện tại
  4. D. Detailed bottom-up effort estimate by the Scrum Master in Story Points based on the User Story complexity