Câu 20: C-TS413-1909: SAP Certified Application Associate – SAP S/4HANA Asset Management
Which statement is correct when planning maintenance work that is to be carried out by an external company?
Nội dung câu hỏi
Which statement is correct when planning maintenance work that is to be carried out by an external company?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. If you assign a control key for an external order operation, the actual values must always be entered as a goods receipt in the system.
- B. A service master record must always be assigned to the external order operation.
- C. In the control key assigned to the order operation, the "Service" indicator must always be activated.
- D. If you assign a control key with indicator "Service" for an external service, you have to enter the actual values via the service entry sheet. — đáp án hiện tại