CertyRush
Đang tải...
C CertyRush
Câu hỏi free preview

Câu 20: C-TS413-1909: SAP Certified Application Associate – SAP S/4HANA Asset Management

Which statement is correct when planning maintenance work that is to be carried out by an external company?

Nội dung câu hỏi

Which statement is correct when planning maintenance work that is to be carried out by an external company?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. If you assign a control key for an external order operation, the actual values must always be entered as a goods receipt in the system.
  2. B. A service master record must always be assigned to the external order operation.
  3. C. In the control key assigned to the order operation, the "Service" indicator must always be activated.
  4. D. If you assign a control key with indicator "Service" for an external service, you have to enter the actual values via the service entry sheet. — đáp án hiện tại

Cộng đồng

0 bình luận công khai. Tên thành viên được ẩn một phần.

Chưa có bình luận. Mở giao diện tương tác để bắt đầu thảo luận.

Câu hỏi liền kề