CertyRush
Đang tải...
C CertyRush
Câu hỏi free preview

Câu 6: C-TS422-2023: SAP Certified Associate - SAP S/4HANA Cloud Private Edition, Production Planning and Manufacturing

You want to set up a make-to-order planning scenario for a finished product. The bill of material contains two components: one should be procured for each sales order individually, and the other should be procured jointly for all independent requirements. Forecasting for the finished product is NOT possible. Which set…

Nội dung câu hỏi

You want to set up a make-to-order planning scenario for a finished product. The bill of material contains two components: one should be procured for each sales order individually, and the other should be procured jointly for all independent requirements. Forecasting for the finished product is NOT possible. Which settings do you make to achieve this?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Choose planning strategy 20 (Make-to-Order) and select the corresponding Individual/Collective indicator. — đáp án hiện tại
  2. B. Choose planning strategy 20 (Make-to-Order) and select the corresponding Mixed MRP indicator.
  3. C. Choose planning strategy 50 (Planning without final assembly) and select the corresponding Individual/Collective indicator.
  4. D. Choose planning strategy 50 (Planning without final assembly) and select the corresponding Mixed MRP indicator.

Cộng đồng

0 bình luận công khai. Tên thành viên được ẩn một phần.

Chưa có bình luận. Mở giao diện tương tác để bắt đầu thảo luận.

Câu hỏi liền kề