Câu 20: SASM: SAFe Advanced Scrum Master 5.1

Three teams in the Agile Release Train are working on the same Feature. Team A is a complicated subsystem team, and Teams B and C are stream-aligned teams. During PI Planning, Teams B and C committed to delivering their part of the Feature by the end of Iteration five and plan to integrate with each other along with T…

Nội dung câu hỏi

Three teams in the Agile Release Train are working on the same Feature. Team A is a complicated subsystem team, and Teams B and C are stream-aligned teams. During PI Planning, Teams B and C committed to delivering their part of the Feature by the end of Iteration five and plan to integrate with each other along with Team A's piece in the first week of the IP Iteration. Why is this an anti-pattern?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Because Product Management accepted each team's final plan at the end of PI Planning Day 2
  2. B. Because each feature team needs to integrate with the component team
  3. C. Because the teams managed their dependencies and planned their integration timing during PI Planning
  4. D. Because work should not be planned for the IP Iteration — đáp án hiện tại