Câu 18: SASM: SAFe Advanced Scrum Master 5.1
A Scrum Master is asked to help an Agile Release Train that has struggled through multiple Pls. They just finished the second Iteration in the current PI and have nothing to show at the System Demo. The ART stakeholders are concerned. What should be done?
Nội dung câu hỏi
A Scrum Master is asked to help an Agile Release Train that has struggled through multiple Pls. They just finished the second Iteration in the current PI and have nothing to show at the System Demo. The ART stakeholders are concerned. What should be done?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Stop working on any new functionality and fully integrate and test the system; adjust scope based on what is learned — đáp án hiện tại
- B. Have every team demonstrate their team increment to the stakeholders separately in the team branch
- C. Find a vendor that specializes in integrating system increments from multiple teams
- D. Re-architect the system so that there are no dependencies between the teams; integration is not required at this time
Cộng đồng
0 bình luận công khai. Tên thành viên được ẩn một phần.
Chưa có bình luận. Mở giao diện tương tác để bắt đầu thảo luận.