Which of the following are true about the length of the Sprint? (Choose two.)

Nội dung câu hỏi

Which of the following are true about the length of the Sprint? (Choose two.)

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. The length of the Sprint should be proportional to the work that is done in between Sprints.
  2. B. It is best to have Sprints of consistent length throughout a development effort. — đáp án hiện tại
  3. C. Sprint length is determined during Sprint Planning, and should hold the time it will take to code the planned features in the upcoming Sprint, but does not include time for any testing.
  4. D. Sprint length is determined during Sprint Planning, and should be long enough to make sure the Development Team can deliver what is to be accomplished in the upcoming Sprint.
  5. E. All Sprints must be 1 month or less. — đáp án hiện tại