Câu 41: PSM II: Professional Scrum Master II
During Sprint Planning, the Definition of Done will help the Development Team forecast the amount of work, selected from the Product Backlog, deemed feasible to make 'done' by the end of the Sprint. Which two items best describes what 'done' means? (Choose two.)
Nội dung câu hỏi
During Sprint Planning, the Definition of Done will help the Development Team forecast the amount of work, selected from the Product Backlog, deemed feasible to make 'done' by the end of the Sprint. Which two items best describes what 'done' means? (Choose two.)
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. All the work needed to prepare the Increment for User Acceptance Testing.
- B. All the work needed to prepare the Increment for Integration Testing.
- C. Having an Increment of working software that is potentially releasable to the end users. — đáp án hiện tại
- D. All the work performed as defined in the Definition of Done. — đáp án hiện tại
- E. All the work completed within the current skills and expertise in the Development Team.