Câu 56: PSM II: Professional Scrum Master II
At the eighth Sprint Review, the stakeholders are upset that the product being built is not what they expected and will incur additional costs that was not planned for. What may have led to this?
Nội dung câu hỏi
At the eighth Sprint Review, the stakeholders are upset that the product being built is not what they expected and will incur additional costs that was not planned for. What may have led to this?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. The Scrum Master has not been reporting on the progress of the Scrum Team. The Product Owner has not been managing the Development Team's tasks effectively. The Development Team has not been improving their velocity.
- B. The Scrum Master has not ensured that the project is transparent. The Product Owner has not made the stakeholders aware of the progress of the project. The stakeholders have not been attending the Sprint Reviews. — đáp án hiện tại
- C. The Scrum Master has not been attending the Daily Standup. The Product Owner has not been using the Gantt chart correctly. The Stakeholders has not been invited to the Sprint Retrospectives.