Câu 1: PSM II: Professional Scrum Master II

Peter, the Product Owner, has been giving positive recognition to individual Development Team members who have moved their work to 'done' during the DailyScrum. Peter wants to ensure the team is adhering to the ideal guideline on the burndown chart. What would be two valid actions for Steven, the Scrum Master, to take…

Nội dung câu hỏi

Peter, the Product Owner, has been giving positive recognition to individual Development Team members who have moved their work to 'done' during the DailyScrum. Peter wants to ensure the team is adhering to the ideal guideline on the burndown chart. What would be two valid actions for Steven, the Scrum Master, to take? (Choose two.)

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Steven talks with Peter about concerns of how his behavior might impact the team members and request that he stop attending for now. — đáp án hiện tại
  2. B. Steven coaches Peter on best practices for updating the burndown chart as it provides accurate information on how well the team is performing.
  3. C. Nothing. Steven is optional at the Daily Scrum and it is the responsibility of the team to decide how to best run it.
  4. D. Steven coaches the Scrum Team about the purpose of the Daily Scrum. — đáp án hiện tại