Câu 28: PSM II: Professional Scrum Master II

A Scrum Team has requested a hardening Sprint to integrate the work produced in previous Sprints and test before releasing. What three scenarios has likely occurred? (Choose three.)

Nội dung câu hỏi

A Scrum Team has requested a hardening Sprint to integrate the work produced in previous Sprints and test before releasing. What three scenarios has likely occurred? (Choose three.)

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. The team's Definition of Done is not being adhered to during every Sprint. — đáp án hiện tại
  2. B. The team's Definition of Done is weak or incomplete causing a build up of technical debt. — đáp án hiện tại
  3. C. The Development Team is having difficulties with the ability to regularly release during a Sprint. — đáp án hiện tại
  4. D. Hardening Sprints are supported by the Scrum framework so this is acceptable.
  5. E. Scrum has been customized in a suitable manner to make the previous work releasable.