Câu 36: PSPO I: Professional Scrum Product Owner I
A Project Manager working with your Scrum Team has raised concerns about progress and money spent. What are the two best responses? (Choose two.)
Nội dung câu hỏi
A Project Manager working with your Scrum Team has raised concerns about progress and money spent. What are the two best responses? (Choose two.)
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Have a discussion with the Project Manager; share the current impediments and forecast for the Sprint. — đáp án hiện tại
- B. Scrum does not have Project Managers so disregard their concerns.
- C. Show the Earned Value Analysis (EVA) report.
- D. Share the last stakeholder briefing document prepared by the Product Owner.
- E. Promote transparency by sharing the Product Backlog and ensuring the Project Manager has access. — đáp án hiện tại