Adding acceptance criteria to each Product Backlog item is a practice many Scrum Teams find useful. Is it the Product Owner’s responsibility to write all of the acceptance criteria for each Product Backlog Items?
Nội dung câu hỏi
Adding acceptance criteria to each Product Backlog item is a practice many Scrum Teams find useful. Is it the Product Owner’s responsibility to write all of the acceptance criteria for each Product Backlog Items?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Yes. the Product Owner is responsible for adding acceptance criteria to Product Backlog items.
- B. No, acceptance criteria should be written by the Developers completing the work.
- C. It depends, the Product Owner is accountable for clearly communicating Product Backlog items but they may delegate the responsibility of writing acceptance criteria to others, or they may do the work themselves. — đáp án hiện tại