Câu 18: PSPO II: Professional Scrum Product Owner II
Which of the following are true about the length of the Sprint? (Choose all that apply.)
Nội dung câu hỏi
Which of the following are true about the length of the Sprint? (Choose all that apply.)
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. It is best to have Sprints of consistent length. — đáp án hiện tại
- B. Sprint length is determined during Sprint Planning and should hold the time it will take to create the planned features in the upcoming Sprint, but does not include time for any validation.
- C. Sprint length is determined during Sprint Planning and should be long enough to make sure the Developers can deliver what is to be accomplished in the upcoming Sprint.
- D. All Sprints must be 1 month or less. — đáp án hiện tại
- E. The length of the Sprint should be proportional to the work that is done in between Sprints.