Câu 6: CDFM-MODULE-2: CDFM Module 2 - Budget and Cost Analysis

According to the Cost as an Independent Variable (CAIV) costing principle, if the cost estimate for a major weapon system rises during the system demonstration period of development, what is DoD expected to do?

Nội dung câu hỏi

According to the Cost as an Independent Variable (CAIV) costing principle, if the cost estimate for a major weapon system rises during the system demonstration period of development, what is DoD expected to do?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Add funding in the next Program Objective Memorandum (POM) submission to obtain a decision from OSD in the Program/Budget process.
  2. B. Add funding to the overall cost of the program since the system is needed.
  3. C. Submit the change to Congress in the next budget for decision by the Congressional Committees.
  4. D. Hold funding level by reducing the number of units or the performance characteristics of the system. — đáp án hiện tại