Câu 10: CDFM-MODULE-3: CDFM Module 3 - Accounting and Finance
An agency contracts for severable services in August. The term of the contract is one year. May the agency award the one-year contract, obligating those funds available in August for the entire term of the one-year contract?
Nội dung câu hỏi
An agency contracts for severable services in August. The term of the contract is one year. May the agency award the one-year contract, obligating those funds available in August for the entire term of the one-year contract?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. No, two separate contracts must be awarded. Each contract must be limited to a specific fiscal year.
- B. Yes, 10 U.S.C. § 2410(a) permits funding a one-year severable service contract crossing fiscal years to be funded with a single-year appropriation. — đáp án hiện tại
- C. No, a severable service contract crossing fiscal years requires separate year appropriations for each part of the contract performed in a different fiscal year.
- D. Yes, but only if the agency knows future year funds will not be available.
Cộng đồng
0 bình luận công khai. Tên thành viên được ẩn một phần.
Chưa có bình luận. Mở giao diện tương tác để bắt đầu thảo luận.