SPC Charts are used extensively in different business and decision-making environments. In this example a vendor is being selected based on speed of delivery. Which of the conclusions would help you pick a vendor for your needs regarding lead-time of delivery from your vendors? (Note: There are 4 correct answers).
Nội dung câu hỏi
SPC Charts are used extensively in different business and decision-making environments. In this example a vendor is being selected based on speed of delivery. Which of the conclusions would help you pick a vendor for your needs regarding lead-time of delivery from your vendors? (Note: There are 4 correct answers).
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Vendor A with a much shorter lead time in delivery
- B. Vendor B as it has a better consistency (lower variance) on lead time — đáp án hiện tại
- C. Vendor B as Vendor A shows a situation out of control as shown in red — đáp án hiện tại
- D. Vendor B as the Control Limits are much narrower than Vendor A — đáp án hiện tại
- E. Vendor B with higher lead time, but a process with much narrower Control Limits — đáp án hiện tại