Process A has a Timer. Process B has a JMS Queue Receiver. Process C has a JMS Topic Subscriber. These processes are to be deployed on two machines and configured to operate in fault-tolerant and load-balanced mode. Which two steps should you take to achieve this configuration? (Choose two.)

Nội dung câu hỏi

Process A has a Timer. Process B has a JMS Queue Receiver. Process C has a JMS Topic Subscriber. These processes are to be deployed on two machines and configured to operate in fault-tolerant and load-balanced mode. Which two steps should you take to achieve this configuration? (Choose two.)

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. bundle the Timer and the JMS Queue Receiver in one EAR file and deploy it in fault-tolerant mode
  2. B. bundle the JMS Topic Subscriber and Timer in one EAR file and deploy it in fault-tolerant mode — đáp án hiện tại
  3. C. put the JMS Queue Receiver in its own EAR and deploy it twice — đáp án hiện tại
  4. D. bundle the two JMS-based starters in one EAR file and deploy it twice
  5. E. put the Timer in its own EAR and deploy it in fault-tolerant mode
  6. F. put the JMS Topic Subscriber in its own EAR file and deploy it twice