The engineer configured Veeam Backup & Replications 3 years ago with an all-in-one physical server with one job backing up all VMs. The environment grew considerably and RPOs are no longer met. The engineer checks the backup job and sees:Load: Source 0% > Proxy 68% > Network 0% > Target 0%.What should be done to decre…
Nội dung câu hỏi
The engineer configured Veeam Backup & Replications 3 years ago with an all-in-one physical server with one job backing up all VMs. The environment grew considerably and RPOs are no longer met. The engineer checks the backup job and sees:Load: Source 0% > Proxy 68% > Network 0% > Target 0%.What should be done to decrease the backup processing time?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Edit the Backup Job settings and enable parallel processing from Advanced options
- B. Split the VMs in several jobs with the same schedule to process the VMs in parallel
- C. From Backup Infrastructure add an extra Windows/Linux machine as Backup Proxy — đáp án hiện tại
- D. Install another Veeam Backup & Replication server and move half of the VMs to be processed in a separate job