Câu 2: Scrum Master Certified (SMC®)
A town has begun a project that involves keeping track of the buses traveling on the roads of the town. Which of the following is NOT a characteristic of this project if it is managed according to Scrum Framework?
Nội dung câu hỏi
A town has begun a project that involves keeping track of the buses traveling on the roads of the town. Which of the following is NOT a characteristic of this project if it is managed according to Scrum Framework?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Detailed upfront planning will be done to ensure that risks are identified early on. — đáp án hiện tại
- B. The team working on this project will meet every day for 15 minutes to list impediments to completing their tasks.
- C. The Product Owner will prioritize the tasks that deliver maximum business value.
- D. The customer does not have to be able to define very concrete requirements early on.