Câu 4: CMM: Certified Construction Manager

An agency CM for the owner of a nationwide gas station chain is overseeing a pilot project to install a wind turbine at an existing station site to power the station. The owner hired an engineering firm to do the design, including a thorough subsurface site investigation. The construction contractor has been hired and…

Nội dung câu hỏi

An agency CM for the owner of a nationwide gas station chain is overseeing a pilot project to install a wind turbine at an existing station site to power the station. The owner hired an engineering firm to do the design, including a thorough subsurface site investigation. The construction contractor has been hired and work is underway. The activities on the critical path of the project are all finish-to-start relationships, and are listed below in chronological order:Excavate for concrete foundation (2 days); form concrete foundation and install reinforcing steel (6 days); pour concrete foundation (1 day); concrete curing period (14 days); strip forms (1 day); erect wind turbine (7 days); connect turbine power line to station (3 days). All other work is complete and these are the only remaining activities. The contract specifies liquidated damages for late completion at a rate of $1,000/day. The contract also specifies that the sole compensation for delays is a stipulated daily extended overhead/general conditions rate of $3,000/day. During the 14-day concrete curing period, one of the gas station pumps was leaking fuel. The gas station and construction site were shut down for 4 days while the gas station had the leak repaired. How many days of time extension and how much compensation is the contractor entitled to for the delay?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. 4 day time extension; $12,000 payment to contractor
  2. B. 4 day time extension; no payment to contractor — đáp án hiện tại
  3. C. 0 day time extension; $12,000 payment to contractor
  4. D. 0 day time extension; no payment to contractor