Câu 3: CMM: Certified Construction Manager
During submittal reviews, the owner decides to make a significant design change to a curtain wall system which happens to be on the critical path of the approved baseline schedule. Which of the following options is available to the owner to address the contractor’s delay claim and maintain the schedule?
Nội dung câu hỏi
During submittal reviews, the owner decides to make a significant design change to a curtain wall system which happens to be on the critical path of the approved baseline schedule. Which of the following options is available to the owner to address the contractor’s delay claim and maintain the schedule?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Time impact analysis
- B. Deductive change order
- C. Acceleration with compensation — đáp án hiện tại
- D. Schedule suspension