Câu 15: CMM: Certified Construction Manager
A relatively new general contractor has executed three projects. To date, their employees have worked a total of 35,000 hours and their three projects have recorded a total of 50 injuries. What is their recordable case rate?
Nội dung câu hỏi
A relatively new general contractor has executed three projects. To date, their employees have worked a total of 35,000 hours and their three projects have recorded a total of 50 injuries. What is their recordable case rate?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. 0.0014
- B. 150
- C. 286 — đáp án hiện tại
- D. 700