Câu 14: CMM: Certified Construction Manager
When the CM assists the owner in prequalifying, evaluating, or screening potential contractors, especially as it relates to safety programs, the CM should evaluate the contractor’s lost time frequency rate; lost time severity average; OSHA 200; OSHA 300; experience modification rate and an up-to-date list of any OSHA…
Nội dung câu hỏi
When the CM assists the owner in prequalifying, evaluating, or screening potential contractors, especially as it relates to safety programs, the CM should evaluate the contractor’s lost time frequency rate; lost time severity average; OSHA 200; OSHA 300; experience modification rate and an up-to-date list of any OSHA citations issued to them in the last three years, including the disposition of each citation. This is important because:
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. extensive documentation is required to demonstrate sufficient due diligence.
- B. contractors only monitor safety if they understand the owner’s emphasis on safety.
- C. a contractor with a poor safety record may increase the owner's risk and worker compensation costs. — đáp án hiện tại
- D. a contractor with a poor safety record is likely to be a low bidder.