Câu 10: CMM: Certified Construction Manager

An inexperienced client on a design-bid-build project states that they do not want the designer to assist in the review of submittals, respond to Requests for Information (RFIs), or conduct any site inspections during the construction phase. How should the CM respond to the client’s request?

Nội dung câu hỏi

An inexperienced client on a design-bid-build project states that they do not want the designer to assist in the review of submittals, respond to Requests for Information (RFIs), or conduct any site inspections during the construction phase. How should the CM respond to the client’s request?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Agree with the client that this will save the project from unnecessary costs and report that the design documents should be error-free.
  2. B. Review the Project Management Plan (PMP) and proceed accordingly.
  3. C. Review the Project Procedures Manual (PPM) and then discuss with the client why their approach may add more risk to the project. — đáp án hiện tại
  4. D. Ignore the client and continue coordinating with the design professional to provide these necessary services as part of their contract.