As the owner’s rep, you are providing on-site construction management services to a municipality for their new design-build city hall project. The design-build team is planning to use a solar panel subcontractor, who unfortunately has an Experience Modification Rate (EMR) of 2. Who is responsible for mitigating the ri…
Nội dung câu hỏi
As the owner’s rep, you are providing on-site construction management services to a municipality for their new design-build city hall project. The design-build team is planning to use a solar panel subcontractor, who unfortunately has an Experience Modification Rate (EMR) of 2. Who is responsible for mitigating the risks associated with this subcontractor’s work activities?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Owner
- B. General contractor — đáp án hiện tại
- C. Owner’s rep
- D. Architect