Câu 273: PK0-004: CompTIA Project+

A company's Chief Executive Officer (CEO) has asked the project manager to update upper management regarding the status of a project. The project manager sends weekly written reports to the CEO and upper management. The project manager receives feedback that several administrators are frustrated with the level of deta…

Nội dung câu hỏi

A company's Chief Executive Officer (CEO) has asked the project manager to update upper management regarding the status of a project. The project manager sends weekly written reports to the CEO and upper management. The project manager receives feedback that several administrators are frustrated with the level of detail and the frequency of the updates. Which of the following is the BEST step for the project manager to take to resolve this issue?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Customize the reports for each administrator in their preferred manner.
  2. B. Set up a meeting with the supervisor to discuss and resolve the issue. — đáp án hiện tại
  3. C. Stop sending reports and wait for upper management to talk to the project manager about their preferences.
  4. D. Start giving verbal reports to upper management so they can hear about the project in person.