Câu 272: PK0-004: CompTIA Project+
A project manager is overseeing the construction of a new building. There are likely existing underground water, gas, and electrical lines. Which of the following is an example of mitigation?
Nội dung câu hỏi
A project manager is overseeing the construction of a new building. There are likely existing underground water, gas, and electrical lines. Which of the following is an example of mitigation?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Trust the contractor to do the job well because the company has been in business for a long time.
- B. Tell the contractor that the company is responsible for any damage done to underground lines.
- C. Immediately fix any broken lines that are hit during construction.
- D. Ensure the contractor has the appropriate utility maps. — đáp án hiện tại
Cộng đồng
0 bình luận công khai. Tên thành viên được ẩn một phần.
Chưa có bình luận. Mở giao diện tương tác để bắt đầu thảo luận.