Câu 212: PK0-004: CompTIA Project+

A concrete pad needs to be laid for a new house and requires three days to cure. The project manager notes that rain may be in the immediate forecast. Which of the following would BEST avoid the risk of rain damage?

Nội dung câu hỏi

A concrete pad needs to be laid for a new house and requires three days to cure. The project manager notes that rain may be in the immediate forecast. Which of the following would BEST avoid the risk of rain damage?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Place a tarp over the fresh concrete to protect it.
  2. B. Refinish the concrete if it rains during that time.
  3. C. Pour the concrete as quickly as possible to allow the most drying time.
  4. D. Wait to pour the concrete until rain is not in the forecast. — đáp án hiện tại