Câu 213: PK0-004: CompTIA Project+
A project manager is developing a risk management plan and has decided to score each risk based on composite score of impact and probability. In discussions with the project sponsor, they determined that all risks with a composite score lower than 1 will not receive further attention. Which of the following risks shou…
Nội dung câu hỏi
A project manager is developing a risk management plan and has decided to score each risk based on composite score of impact and probability. In discussions with the project sponsor, they determined that all risks with a composite score lower than 1 will not receive further attention. Which of the following risks should the project manager accept? (Choose two.)
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. 1
- B. 2
- C. 3 — đáp án hiện tại
- D. 4
- E. 5 — đáp án hiện tại
- F. 6
Cộng đồng