Câu 291: PK0-004: CompTIA Project+
A sponsor requests that the project team shorten the completion of a project by two months to give the sales team more leverage in renegotiating the contract with the client. The budgeted time is 500 hours, and the projected earned value is $30,000. Which of the following represents the cost variance for both project…
Nội dung câu hỏi
A sponsor requests that the project team shorten the completion of a project by two months to give the sales team more leverage in renegotiating the contract with the client. The budgeted time is 500 hours, and the projected earned value is $30,000. Which of the following represents the cost variance for both project completions?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. גˆ’$4.8K and גˆ’$7K
- B. גˆ’$4.9K and $7K
- C. $4.8K and גˆ’$7K — đáp án hiện tại
- D. $4.8K and $7K