Câu 291: PK0-004: CompTIA Project+

A sponsor requests that the project team shorten the completion of a project by two months to give the sales team more leverage in renegotiating the contract with the client. The budgeted time is 500 hours, and the projected earned value is $30,000. Which of the following represents the cost variance for both project…

Nội dung câu hỏi

A sponsor requests that the project team shorten the completion of a project by two months to give the sales team more leverage in renegotiating the contract with the client. The budgeted time is 500 hours, and the projected earned value is $30,000. Which of the following represents the cost variance for both project completions?

Minh họa câu hỏi

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. גˆ’$4.8K and גˆ’$7K
  2. B. גˆ’$4.9K and $7K
  3. C. $4.8K and גˆ’$7K — đáp án hiện tại
  4. D. $4.8K and $7K