Câu 292: PK0-004: CompTIA Project+

The internal project sponsor is frustrated by a lack of concise, regular updates regarding the status of a project. Which of the following changes would BEST satisfy the project sponsor?

Nội dung câu hỏi

The internal project sponsor is frustrated by a lack of concise, regular updates regarding the status of a project. Which of the following changes would BEST satisfy the project sponsor?

Minh họa câu hỏi

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Add the project sponsor to all project email correspondence moving forward
  2. B. Include the project sponsor in all project meetings moving forward
  3. C. Add a new line to the communications plan to provide a weekly status report with a dashboard — đáp án hiện tại
  4. D. Include the project sponsor in the daily stand-up with the entire project team