Câu 89: PK0-005: CompTIA Project+
A project manager has been assigned to a project that involves replacing key operational equipment. The project manager is new to the industry and has learned that compliance requirements must be met. Which of the following should the project manager do FIRST?
Nội dung câu hỏi
A project manager has been assigned to a project that involves replacing key operational equipment. The project manager is new to the industry and has learned that compliance requirements must be met. Which of the following should the project manager do FIRST?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Trust that the project requirements fully document the necessary compliances.
- B. Meet with the end users to learn more about the compliance requirements.
- C. Research the compliance requirements related to the project to understand the implications. — đáp án hiện tại
- D. Make the QA specialist responsible for ensuring that the compliance requirements are met.
Cộng đồng
0 bình luận công khai. Tên thành viên được ẩn một phần.
Chưa có bình luận. Mở giao diện tương tác để bắt đầu thảo luận.