Câu 90: PK0-005: CompTIA Project+

A project manager is assigned to a large, complex project that is very new to the organization. Because of huge expenditures, the project cannot be cancelled after it starts. Which of the following is most important for the project manager to do FIRST?

Nội dung câu hỏi

A project manager is assigned to a large, complex project that is very new to the organization. Because of huge expenditures, the project cannot be cancelled after it starts. Which of the following is most important for the project manager to do FIRST?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Carefully select the vendor.
  2. B. Identify and evaluate risks. — đáp án hiện tại
  3. C. Establish change management procedures.
  4. D. Evaluate the resource pool.