Câu 5: CSM-001: Certified Scrum Master
Why does Scrum prevent Product Owners from changing Product Backlog items that are being worked on during the Sprint?
Nội dung câu hỏi
Why does Scrum prevent Product Owners from changing Product Backlog items that are being worked on during the Sprint?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. The development team cannot meet their Sprint commitment to complete work if requirements are changing
- B. A Sprint cycle is not enough time for senior management review and approve changes
- C. This forces Product Owners to focus on what is really important for the team to develop. — đáp án hiện tại
- D. The development team must be able to limit the Product Owner authority
Cộng đồng
0 bình luận công khai. Tên thành viên được ẩn một phần.
Chưa có bình luận. Mở giao diện tương tác để bắt đầu thảo luận.