CertyRush
Đang tải...
C CertyRush
Câu hỏi free preview

Câu 6: CSM-001: Certified Scrum Master

You are the Scrum Master. The Sprint will complete in two days. Each day of the Sprint is equivalent to 8 hours. The team has just enough time to complete all tasks in the remaining 16 hours with the exception of three tasks. Of these three tasks, two tasks (a total of 6 hours) are required to complete one Product Bac…

Nội dung câu hỏi

You are the Scrum Master. The Sprint will complete in two days. Each day of the Sprint is equivalent to 8 hours. The team has just enough time to complete all tasks in the remaining 16 hours with the exception of three tasks. Of these three tasks, two tasks (a total of 6 hours) are required to complete one Product Backlog item and one task (an estimate of 2 hours) is required to complete another Product Backlog item. How should the development team handle the remaining three tasks?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. The development team should negotiate with the Product Owner on the definition of "done".
  2. B. The development team should work the extra 8 hours to complete their commitment to the Product Owner
  3. C. The development team should place the two Product Backlog items back onto the Product Backlog — đáp án hiện tại
  4. D. The development team should keep the three tasks on the Sprint Backlog for the next Sprint and complete those tasks first

Cộng đồng

0 bình luận công khai. Tên thành viên được ẩn một phần.

Chưa có bình luận. Mở giao diện tương tác để bắt đầu thảo luận.

Câu hỏi liền kề