Câu 104: GCPM: GIAC Certified Project Manager
Billy is the project manager of the PQW Project and she has an assigned project budget of $655,000. Currently she is 80 percent complete with the project though she was scheduled to be 100 percent done by this date. She has spent $490,000 to date and other than the project schedule, which was delayed because of a vend…
Nội dung câu hỏi
Billy is the project manager of the PQW Project and she has an assigned project budget of $655,000. Currently she is 80 percent complete with the project though she was scheduled to be 100 percent done by this date. She has spent $490,000 to date and other than the project schedule, which was delayed because of a vendor, the project is going well. What should Billy report as her schedule performance index for this project?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. 80 — đáp án hiện tại
- B. 1.23
- C. 100 percent because the vendor caused her lateness
- D. $524,000
Cộng đồng
0 bình luận công khai. Tên thành viên được ẩn một phần.