Câu 103: GCPM: GIAC Certified Project Manager
Sasha is the project manager of a large construction project. She is finalizing ground rules, training, and team-building activities for her project team members. In which of the following processes is she working on?
Nội dung câu hỏi
Sasha is the project manager of a large construction project. She is finalizing ground rules, training, and team-building activities for her project team members. In which of the following processes is she working on?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Manage Project Team
- B. Plan Human Resource Management
- C. Acquire Project Team
- D. Develop Project Team — đáp án hiện tại
Cộng đồng
0 bình luận công khai. Tên thành viên được ẩn một phần.
Chưa có bình luận. Mở giao diện tương tác để bắt đầu thảo luận.