Câu 131: CBAP: Certified Business Analysis Professional

During a prioritization meeting, a business analyst (BA) mentioned that the access management system requirements are not stable. The project manager and a team lead proposed removing the requirements from discussion. A domain subject matter expert (SME) insisted on making that requirement a high priority, because it…

Nội dung câu hỏi

During a prioritization meeting, a business analyst (BA) mentioned that the access management system requirements are not stable. The project manager and a team lead proposed removing the requirements from discussion. A domain subject matter expert (SME) insisted on making that requirement a high priority, because it is really important from their point of view. What should the BA do?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Make the requirement a lower priority to minimize unanticipated rework and wasted effort
  2. B. Set the requirements at a high priority to adhere to the SME's point of view
  3. C. Remove the requirement from the project
  4. D. Leave priority unfilled for these requirements — đáp án hiện tại