Testing Process -Which of the following is an example of the test closure activity indicated as "lessons learned"?

Nội dung câu hỏi

Testing Process -Which of the following is an example of the test closure activity indicated as "lessons learned"?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Archive all the test results of the acceptance testing phase
  2. B. Deliver a list of the open defects of a software product released into production to the service desk team
  3. C. Participate in a meeting at the end of a project aimed at better managing the events and problems of future projects — đáp án hiện tại
  4. D. Deliver an automated regression test suite, used during the system test phase of a software product released into production, to the team responsible for maintenance testing