Câu 16: ITIL 4 Specialist: Collaborate, Assure and Improve
An organization is preparing a large project which will include procurement of many external services. Which of the supplier management activities is LEAST LIKELY to be delegated to a third party in this project?
Nội dung câu hỏi
An organization is preparing a large project which will include procurement of many external services. Which of the supplier management activities is LEAST LIKELY to be delegated to a third party in this project?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Documenting how supplier management activities will be performed — đáp án hiện tại
- B. Onboarding a new supplier
- C. Monitoring how well a supplier is delivering services
- D. Reviewing possible suppliers and creating a shortlist