Câu 22: 74-343: Managing Projects with Microsoft Project 2013

You are a manager for an organization that uses Project Professional 2013. A critical project shows average finish variance values between 5-10 days for the tasks. You need to interpret these variance values to determine the next course of action to take. What do these variance values mean?

Nội dung câu hỏi

You are a manager for an organization that uses Project Professional 2013. A critical project shows average finish variance values between 5-10 days for the tasks. You need to interpret these variance values to determine the next course of action to take. What do these variance values mean?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. The project is on schedule.
  2. B. The project is running between 5-10 days ahead of schedule.
  3. C. The project is running between 5-10 days behind schedule. — đáp án hiện tại
  4. D. The project is averaging a normal performance timeline.