Câu 23: 74-343: Managing Projects with Microsoft Project 2013

You are a project manager who uses Project Professional 2013. When viewing the critical path, you notice that there are some inconsistencies. To investigate the status of the critical path, you insert the Total Slack column into a task table. You discover that many of the tasks have negative Total Slack values. You ne…

Nội dung câu hỏi

You are a project manager who uses Project Professional 2013. When viewing the critical path, you notice that there are some inconsistencies. To investigate the status of the critical path, you insert the Total Slack column into a task table. You discover that many of the tasks have negative Total Slack values. You need to resolve the negative Total Slack values. What should you do?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Remove lag time from task relationships.
  2. B. Remove as many constraints as possible. — đáp án hiện tại
  3. C. Re-assign resources that have more availability at the time of the negative slack.
  4. D. Remove lead time from the task relationships.