CertyRush
Đang tải...
C CertyRush
Câu hỏi free preview

Câu 24: 74-343: Managing Projects with Microsoft Project 2013

You manage a project by using Project Professional 2013. A critical task is out of scope for the project. The stakeholders suggest that the task be removed from the project but kept in the plan in case the task is needed in the future. You need to implement a solution to meet the stakeholder's request. What should you…

Nội dung câu hỏi

You manage a project by using Project Professional 2013. A critical task is out of scope for the project. The stakeholders suggest that the task be removed from the project but kept in the plan in case the task is needed in the future. You need to implement a solution to meet the stakeholder's request. What should you do?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Click on the task, and click Inactivate. — đáp án hiện tại
  2. B. Move the task to after the ending date for the project.
  3. C. Delete the task from the schedule.
  4. D. Click the Unlink Task button to unlink the predecessors and successors for the task.

Cộng đồng

0 bình luận công khai. Tên thành viên được ẩn một phần.

Chưa có bình luận. Mở giao diện tương tác để bắt đầu thảo luận.

Câu hỏi liền kề