Câu 25: 74-343: Managing Projects with Microsoft Project 2013

You manage a project by using Project Professional 2013. The work variance for a task is 48 hours. The remaining work is 25 hours. The work for this task has been completed. You need the work variance to be adjusted to reflect what has occurred during the performance of the task. What should you do?

Nội dung câu hỏi

You manage a project by using Project Professional 2013. The work variance for a task is 48 hours. The remaining work is 25 hours. The work for this task has been completed. You need the work variance to be adjusted to reflect what has occurred during the performance of the task. What should you do?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Adjust the value in the Baseline Work column.
  2. B. Enter a 0 in the remaining Duration column. — đáp án hiện tại
  3. C. Adjust the value in the Work Variance column.
  4. D. Mark the task inactive.