Câu 25: 74-343: Managing Projects with Microsoft Project 2013
You manage a project by using Project Professional 2013. The work variance for a task is 48 hours. The remaining work is 25 hours. The work for this task has been completed. You need the work variance to be adjusted to reflect what has occurred during the performance of the task. What should you do?
Nội dung câu hỏi
You manage a project by using Project Professional 2013. The work variance for a task is 48 hours. The remaining work is 25 hours. The work for this task has been completed. You need the work variance to be adjusted to reflect what has occurred during the performance of the task. What should you do?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Adjust the value in the Baseline Work column.
- B. Enter a 0 in the remaining Duration column. — đáp án hiện tại
- C. Adjust the value in the Work Variance column.
- D. Mark the task inactive.
Cộng đồng
0 bình luận công khai. Tên thành viên được ẩn một phần.
Chưa có bình luận. Mở giao diện tương tác để bắt đầu thảo luận.